§ 82-262. Permit application.  


Latest version.
  • (a)

    All industrial users required to obtain a permit shall submit the following information on the application form supplied by the superintendent:

    (1)

    Name, address, and location (if different than address).

    (2)

    Whether the user is a corporation, partnership, proprietorship, or other type of entity, and the name of the persons responsible for discharges by the user.

    (3)

    Standard industrial classification (SIC) code of both the industry (or use) as a whole and any process for which categorical pretreatment standards have been promulgated.

    (4)

    Wastewater constituents and characteristics including, without limitation, any pollutants which are limited or regulated by any federal, state or local standards or requirements. Sampling and analysis shall be performed in accordance with procedures established by the United States EPA and contained in 40 CFR, part 136.

    (5)

    Time and duration of contribution.

    (6)

    Daily maximum and monthly average wastewater flow rates including daily, monthly and seasonal variations, if any.

    (7)

    Site plans, floor plans, mechanical and plumbing plans, and details to show all sewers, sewer connections, floor drains and appurtenances by size, location, and elevation.

    (8)

    Description of activities, facilities, and plant processes on the premises, including a list of all raw materials and chemicals used at the facility which are, or could accidentally or intentionally be, discharged into the POTW.

    (9)

    Each product produced by type, amount, process, and rate of production, as relevant to pretreatment standards and requirements.

    (10)

    Type and amount of raw materials processed (average and maximum per day), including copies of material safety data sheets.

    (11)

    Number and type of employees, and hours of operation, and proposed or actual hours of operation of the pretreatment system.

    (12)

    A listing of and copies of all environmental permits held by the user applicable to the premises for which the permit is being sought.

    (13)

    Whether additional operation and maintenance (O&M) and/or additional pretreatment is required for the user to meet all applicable federal, state, and local standards and requirements. If additional O&M or additional pretreatment will be required to meet the applicable standards and requirements, then the user shall indicate the shortest time schedule necessary to accomplish installation or adoption of additional O&M and/or pretreatment. The completion date in this schedule shall not be later than the compliance date established for the applicable pretreatment standard. The following conditions shall apply to the schedule:

    a.

    The schedule shall contain increments of progress in the form of dates for the commencement and completion of major events and operations of additional pretreatment required for the user to meet the applicable pretreatment standards (including, without limitation, hiring an engineer, completing preliminary plans, completing final plans, and executing contracts).

    b.

    No increment referred to in subsection a. of this section shall exceed nine months, nor shall the total compliance exceed 18 months.

    c.

    No later than 14 days following each date in the schedule and the final date for compliance, the user shall submit a progress report to the superintendent including, at the minimum, whether or not it complied with the increment of progress, the reason for any delay, and if appropriate, the steps being taken by the user to return to the established schedule. In no event shall more than nine months be allowed between submission of the progress report to the superintendent.

    (14)

    Any other information as may be deemed by the city to be necessary to adequately evaluate the permit application. To the extent that actual data is not available for a new source, the applicant shall supply estimated or expected information.

    (b)

    All site plans, floor plans, or other plans required to be submitted as a part of the application shall be prepared and sealed by a licensed engineer.

    (c)

    All applications shall be signed and certified as provided in section 82-341.

(Ord. No. 346, § 2, 4-22-02)